Police Headquarters

Identification

Police Headquarters
169514

Map

Structure in General

high-rise building
demolished [destroyed]
steel
modernism

Usages

police headquarters

Facts

  • The upper levels of the building were demolished using rubber-tracked excavators and skid steer loaders; a Favco tower crane removed the precast elements.
  • To minimize dust blowing throughout the locality, the building was fully enclosed for the whole demolition process.
  • On a daily basis between 45-55 semi-trailers removed rubble from the site.
  • All of the removed building material was recycled, with the exception of the carpets and the building’s ceiling tiles.
  • Because the majority of the building material was recycled, this project was awarded the 2002 Construction Excellence up to $2 million award by SA Case Earth.
  • When demolition reached level 6, a ramp was built that enabled a 65 tonne excavator fitted with an extended arm to reach up and demolish the structure.
  • The central core than contained the lift shafts and stairs was the last section of the building to be demolished.

Do you need more information about this building and its related companies?

More Information

Location

1 Angas Street
1 Angas Street
5000
Adelaide
South Australia
Australia

Technical Data

131.23 ft
12
1964